Clearance
Cutting busbar air clearance with insulation
A bare bar is published as one clearance figure per voltage. Sleeve it and the figure splits in two — and phase-to-earth becomes the wider of the pair.
Phase-to-earth is the binding gap on a sleeved bar. In every row of the manufacturer's clearance table the earth figure exceeds the phase figure — 45 mm against 35 mm at 12 kV on heavy wall, 190 mm against 140 mm at 36 kV. The uninsulated column is published as a single figure per voltage, so that split only appears once the sleeve is on.
The absolute saving climbs with voltage; the proportion does not. Heavy wall holds 35 mm phase-to-phase at 12 kV against 120 mm bare and 140 mm at 36 kV against 320 mm, so the gap is worth 85 mm at the bottom of the range and 180 mm at the top while staying between 29 and 44 per cent of the bare figure throughout. The published table starts at 12 kV and carries no LV row — the saving is a switchgear line item.
Rectangular bar, clearance with insulation
| Voltage | Bare bar, IEC 71-2 | GMB phase-phase | GMB phase-earth | GHB phase-phase | GHB phase-earth |
|---|---|---|---|---|---|
| 12 kV | 120 mm | 65 mm | 75 mm | 35 mm | 45 mm |
| 17.5 kV | 160 mm | 85 mm | 105 mm | 55 mm | 65 mm |
| 24 kV | 220 mm | 115 mm | 150 mm | 70 mm | 100 mm |
| 36 kV | 320 mm | 200 mm | 285 mm | 140 mm | 190 mm |
The manufacturer publishes one clearance table covering both conductor shapes; this is its rectangular half. The uninsulated column is stated to IEC 71-2 and is given as one figure per voltage, not split between the two gaps. Source: the BUSTUBE product page.
Round and tubular bar, same table
| Voltage | Bare bar, IEC 71-2 | GMB phase-phase | GMB phase-earth | GHB phase-phase | GHB phase-earth |
|---|---|---|---|---|---|
| 12 kV | 120 mm | 55 mm | 65 mm | 30 mm | 40 mm |
| 17.5 kV | 160 mm | 70 mm | 85 mm | 50 mm | 60 mm |
| 24 kV | 220 mm | 95 mm | 125 mm | 60 mm | 90 mm |
| 36 kV | 320 mm | 150 mm | 205 mm | 130 mm | 180 mm |
The other half of the same published table. The uninsulated column is the one figure given for that voltage and is not restated per shape, so the bare comparator is identical in both halves.
The shape penalty is a medium-wall problem
Round conductor clears tighter than rectangular at every voltage in both grades: a rolled edge concentrates the field, a cylinder does not. On heavy wall the difference is 5 mm at 12 and 17.5 kV and 10 mm at 24 and 36 kV — inside drawing tolerance, and no reason to change conductor.
On medium wall it opens up. The rectangular figure runs 10 mm wider at 12 kV, 20 mm at 24 kV and 50 mm at 36 kV phase-to-phase, and 80 mm wider at 36 kV phase-to-earth. A 36 kV medium-wall layout drawn on the rectangular rows and built with tubular bar is carrying 50 mm on each phase gap and 80 mm on each earth gap that the published data does not ask for.
Read the row for the grade on the order
The table carries a medium-wall row at 36 kV. The medium-wall grade is published to 24 kV. Take the voltage rating from the grade and the clearance from the row belonging to it — a GMB figure read at 36 kV is a table row, not a rating.
Thin wall carries no clearance column at all: GSC is a 3.3 kV part specified for covering, not for spacing. Above 36 kV the standard range stops and the separate GEHB series takes over at 390 mm phase-to-phase and 520 mm phase-to-earth against 630 mm uninsulated, on a 6.2 mm wall supplied in 1500 mm lengths.
Heavy wall buys the difference with 0.70 mm of extra material. GMB 100/38 is a 3.00 mm wall and GHB 100/38 is 3.70 mm, and the 60 mm gained in the 36 kV phase-to-phase row is what that 0.70 mm is for. The heavier grade also recovers across a narrower band of bar, so the size code often steps up with it — worked through on the size chart.
What 36 kV costs in enclosure width
Clearance arithmetic on the published figures — three rectangular bars in a row, heavy wall against bare. Bar width, support insulators, barriers and working space are extra and none of them is counted here.
| At 36 kV | Bare bar | GHB heavy wall |
|---|---|---|
| Phase-to-phase gap | 320 mm | 140 mm |
| Phase-to-earth gap | 320 mm | 190 mm |
| Two phase gaps, between the outer bars | 640 mm | 280 mm |
| Two earth gaps, outer bar to side wall | 640 mm | 380 mm |
| Width attributable to clearance | 1,280 mm | 660 mm |
Where the 620 mm goes
620 mm comes out of the enclosure at 36 kV before a millimetre of copper is counted. On a switchboard that is a section boundary moving; on a rising main it is a smaller shaft opening. Sheet metal, doors, gaskets and shipping volume all follow that one dimension.
Watch where the residue sits. The phase gaps give back 360 mm and the earth gaps 260, but the insulated side inverts: 380 mm is now going to the two side walls against 280 mm between the bars. Pulling the panel narrower past this point is a wall-clearance problem, not a phase-spacing one.
Copper follows the width. Phase centres set the length of every cross-connection, dropper and tee in the run, so drawing the phases in shortens bar that is bought by the kilogram. The manufacturer makes the same case from the joint end on the moulded shroud range, where covering a connection is offered as the route to a smaller panel and shorter busbar lengths rather than as a safety measure on its own.
The saving is only real if it survives the joints. Spacing is set by the widest live geometry in the run, so a sleeved straight length with an uncovered tee is spaced by the tee and the tables above have bought nothing. The shroud that covers that tee runs a 1.0 mm minimum wall at 12 kV, 1.4 mm at 18 kV, 1.8 mm at 24 kV and 2.5 mm at 36 kV.
A clearance saving is not a thermal saving
A sleeve puts cross-linked polyolefin between copper and moving air. Nothing in this range publishes a derating factor, a temperature rise or a current-carrying figure for a covered bar, and this page does not estimate one. The published thermal figures belong to the material: continuous service from −40 °C to +115 °C and a shrink temperature of 125 °C, both to IEC 216. Size the bar for current on your own calculation, then insulate it. What the covering costs a maintenance team is worked through under insulated against bare busbar.
What decides the number you may put on the drawing
The tables report what the material achieves under test. Not one of the six below is in them.
- The design standard the assembly is certified to. IEC 71-2 supplies the uninsulated baseline above; the switchgear standard the panel is signed off against is what an inspector reads.
- The type test. A reduced gap holds because the assembly passed power-frequency and impulse withstand with the sleeve fitted. The sleeve itself is qualified to ANSI C37.20.2 for switchgear application up to 36 kV — that is the material's certification, not the panel's.
- The purchaser's own specification. An end user or utility can set a gap above the standard minimum and can decline an insulation-based reduction outright. Settle that before the enclosure is drawn, not after.
- Access and working space. A gap that clears dielectrically can still be too narrow to land a torque wrench on the joint. Clearance sets a floor under phase spacing, not the final figure.
- Every joint covered. Tees, elbows and bolted laps need a shroud, cap or sheet of their own before the reduced spacing means anything.
- Pollution, condensation and vermin. A narrow gap behaves differently once the enclosure is dirty, which is a failure-mode question rather than a dimensional one.
Where this goes next
- Busbar sleeve size chartThirty-nine GSC, GMB and GHB codes against width plus breadth. Fix the code before committing the spacing.
- Insulated against bare busbarInspection, repair and fault behaviour — what a maintenance team gains and loses. The millimetres stay on this page.
- The standards a busbar sleeve is tested toANSI C37.20.2, IEC 71-2, IEC 216 and the ASTM methods behind every figure quoted here.
- GEHB 66 kV busbar sleeveThe 390 / 520 / 630 mm set on a 6.2 mm wall, and why it is a separate series.
- The sleeve that shrinks onto the barThree wall grades, what each is rated to, and where the wall figures used above come from.
- Walking a panel, a bus duct and a transformer terminal boxWhere a saved 620 mm shows up in a real enclosure, and where it does not.
Send a bar section and a voltage
A clearance question is answerable in one reply when it carries the bar section in millimetres, the conductor shape, the system voltage and the standard the panel is built to. Without those four it becomes a six-email thread.
Stated limit
This page does not certify a panel. It reports the clearances a manufacturer publishes for two sleeve grades and the uninsulated baseline they are quoted against; what a panel may actually be built to is settled by its design standard and its type test. It says nothing about the current the bar carries once it is covered, because nothing in this product range publishes that. The enclosure-width table is arithmetic on the published clearances and not a manufacturer's figure.
ANSI C37.20.2, IEC 71-2 and IEC 216 are decoded once, on the standards page, and are not repeated beside each value here.